Question: Consider the following project data. Activity Predecessor A M B C A D B E B F B G C. D H E I F

Consider the following project data. Activity
Consider the following project data. Activity
Consider the following project data. Activity Predecessor A M B C A D B E B F B G C. D H E I F J G, H K I a) Find the critical path of the project with PERT. M6 A B 4 8 2 8 4 1 7 3 6 12 9 5 15 10 7 18 12 5 12 9 1 3 2 2 6 10 20 6 11 M 3 15 9 b) What is the probability that the project will be completed within 40 days