Question: Learning Outcome(s): Question Consider the following project activities: Activity Predecessor Duration (DAY) CLO2: State the best practices in the IT project management processes. 4 A

Learning Outcome(s): Question Consider the

Learning Outcome(s): Question Consider the following project activities: Activity Predecessor Duration (DAY) CLO2: State the best practices in the IT project management processes. 4 A 3 B A 3 A 5 D B 2 E 1 F D, E 6 Q CLO3: Develop a comprehensive IT project plan for estimation, scheduling, communication, resource management, procurement, risk, and quality. 5 F, G H Fill the following Cells: Activity ES EF LS LF Slack Time A B D E F G H

Step by Step Solution