Question: Consider the following project. Develop the project schedule using the critical path method, indicating the early start, early finish, late start, late finish, and slack
Consider the following project. Develop the project schedule using the critical path method, indicating the early start, early finish, late start, late finish, and slack for each activity. What is the project duration, and which activities are critical? As a hint, note that both activities A and B have no predecessor activities. #2 Consider the following project. Develop the project schedule using the critical path method, indicating the early start, early finish, late start, late finish, and slack for each activity. What is the project duration, and which activities are critical? As a hint, note that both ectivities A and B have no predecessor activities, and both activities H and J have no successor activities