Question: table [ [ Activity , Predecessor ( s ) , Duration ( days ) ] , [ A , - , 4 ] ,

\table[[Activity,Predecessor(s),Duration (days)],[A,-,4],[B,-,3],[C,A, BI,5],[D,B,4],[E,C,4],[F,D, E,7],[G,E,6],[H,F, G,4],[I,D,9],[J,G, I,6]]
Develop the project schedule using the critical path method, indicating the early start, carly finish, late start, late finish, and slack for each activity. What is the project duration, and which activities are critical? s a hint, note that both activities and B have no predecessor activities, and both activities H and J have no successor activities.
 \table[[Activity,Predecessor(s),Duration (days)],[A,-,4],[B,-,3],[C,A, BI,5],[D,B,4],[E,C,4],[F,D, E,7],[G,E,6],[H,F, G,4],[I,D,9],[J,G, I,6]] Develop the project schedule using

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!