Question: table [ [ Activity , Predecessor ( s ) , Duration ( days ) ] , [ A , - , 4 ] ,
tableActivityPredecessorsDuration daysABCA BIDBECFD EGEHF GIDJG I,
Develop the project schedule using the critical path method, indicating the early start, carly finish, late start, late finish, and slack for each activity. What is the project duration, and which activities are critical? s a hint, note that both activities and have no predecessor activities, and both activities and have no successor activities.