Question: Consider the following project information: Activity Immediate Predecessors Optimistic Time (o) Most likely Time (m) Pessimistic Time (p) A none 4 7 9 B none
Consider the following project information:
| Activity | Immediate Predecessors | Optimistic Time (o) | Most likely Time (m) | Pessimistic Time (p) |
| A | none | 4 | 7 | 9 |
| B | none | 3 | 5 | 8 |
| C | A | 2 | 4 | 6 |
| D | A, B | 6 | 9 | 9 |
| E | C, D | 5 | 5 | 5 |
| F | B | 2 | 5 | 9 |
| G | E, F | 3 | 3 | 6 |
1. What is the expected project completion time?
2. What is the standard deviation of the critical path's time?
3. What is the probability that the project will be completed in 25 weeks?
Step by Step Solution
3.42 Rating (152 Votes )
There are 3 Steps involved in it
To solve this problem we will employ the Program Evaluation and Review Technique PERT to calculate the expected project completion time the standard d... View full answer