Question: Consider the following project tasks and their identified best, likely, and worst-case estimates of task duration. Assume the organization you work for computes TE based
Consider the following project tasks and their identified best, likely, and worst-case estimates of task duration. Assume the organization you work for computes TE based on the standard beta distribution formula. Calculate the TE for each of the following tasks (round to the nearest integer).
Step by Step Solution
3.32 Rating (161 Votes )
There are 3 Steps involved in it
Using the Beta distribution for probabilistic estimation the formula is given as TE a 4m b6 wher... View full answer