Question: Consider the following project management problem: Task Immediate Predecessor(s) Duration (Days) A none 1 B none 3 C A 6 D A 3 E B,
Consider the following project management problem:
| Task | Immediate Predecessor(s) | Duration (Days) |
| A | none | 1 |
| B | none | 3 |
| C | A | 6 |
| D | A | 3 |
| E | B, D | 4 |
| F | C, E | 1 |
Draw the diagram and use the CPM Method to answer each part.
a. What is the expected completion time of this project?
b. What is the critical path through this project?