Question: Consider the following project management problem: Task Immediate Predecessor(s) Duration (Days) A none 1 B none 3 C A 6 D A 3 E B,

Consider the following project management problem:

Task Immediate Predecessor(s) Duration (Days)
A none 1
B none 3
C A 6
D A 3
E B, D 4
F C, E 1

Draw the diagram and use the CPM Method to answer each part.

a. What is the expected completion time of this project?

b. What is the critical path through this project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!