Question: 1 Consider the following project management problem: Task Immediate Predecessor(s) Duration (Days) A none B none 3 C A 6 D 3 E B, D

1 Consider the following project management
1 Consider the following project management problem: Task Immediate Predecessor(s) Duration (Days) A none B none 3 C A 6 D 3 E B, D F CE a. What is the expected completion time of this project? b. What is the critical path through this project? 4 1