Question: Task Immediate Predecessors Optimistic Most probable Pessimistic Crash Time Normal Cost (100) Crash Cost (100) A - 5 6 7 4 10 19 B -

Task

Immediate Predecessors

Optimistic

Most probable

Pessimistic

Crash

Time

Normal

Cost (100)

Crash

Cost (100)

A

-

5

6

7

4

10

19

B

-

7

8

15

7

10

18

C

A, B

3

4

5

2

15

27

D

C

9

10

23

8

20

32

E

C

8

10

12

7

50

80

F

E

5

6

7

4

30

41

G

C

5

6

19

5

80

102.5

H

D, F, G

5

6

7

4

50

64

I

D, F

3

6

15

4

100

124

J

H

2

4

6

3

40

44

K

I, J

3

4

5

3

50

55

  1. Draw a project network
  2. Find the critical path and expected project completion time.
  3. Assuming that management desire a 21 weeks project completion time. What activity should be crashed?
  4. Activity schedule table after crashing.
  5. Find total project cost after crashing.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!