Question: Task Immediate Predecessors Optimistic Most probable Pessimistic Crash Time Normal Cost (100) Crash Cost (100) A - 5 6 7 4 10 19 B -
| Task | Immediate Predecessors | Optimistic | Most probable | Pessimistic | Crash Time | Normal Cost (100) | Crash Cost (100) |
| A | - | 5 | 6 | 7 | 4 | 10 | 19 |
| B | - | 7 | 8 | 15 | 7 | 10 | 18 |
| C | A, B | 3 | 4 | 5 | 2 | 15 | 27 |
| D | C | 9 | 10 | 23 | 8 | 20 | 32 |
| E | C | 8 | 10 | 12 | 7 | 50 | 80 |
| F | E | 5 | 6 | 7 | 4 | 30 | 41 |
| G | C | 5 | 6 | 19 | 5 | 80 | 102.5 |
| H | D, F, G | 5 | 6 | 7 | 4 | 50 | 64 |
| I | D, F | 3 | 6 | 15 | 4 | 100 | 124 |
| J | H | 2 | 4 | 6 | 3 | 40 | 44 |
| K | I, J | 3 | 4 | 5 | 3 | 50 | 55 |
- Draw a project network
- Find the critical path and expected project completion time.
- Assuming that management desire a 21 weeks project completion time. What activity should be crashed?
- Activity schedule table after crashing.
- Find total project cost after crashing.