Question: Consider the following project, using excel solver: Activity Normal Time (Days) Crash Time (Days) Normal Cost ($) Crash Cost ($) Immediate Predecessors A 3 2
Consider the following project, using excel solver:
Activity
Normal Time (Days)
Crash Time (Days) Normal Cost ($) Crash Cost ($) Immediate Predecessors A 3 2 1,000 1,600 - B 2 1 2,000 2,700 - C 2 1 300 600 - D 7 3 1,300 1,600 A E 6 3 850 1,000 B F 2 1 4,000 5,000 C G 4 2 1,500 2,000 D,E
Construct the pert network
Determine the critical path and project completion time
Determine the cost of crashing the project to 10 days