Question: Consider the following project network: Normal Crash Activity Time (normal) Cost (normal) Time (crash) Cost (crash) Cost Slope A 4 50 4 50 -- B

Consider the following project network:

Normal

Crash

Activity

Time(normal)

Cost(normal)

Time(crash)

Cost(crash)

Cost Slope

A

4

50

4

50

--

B

9

60

5

120

15

C

6

70

3

100

10

D

9

40

6

100

20

E

4

100

2

150

25

F

5

90

4

120

30

G

3

80

3

80

--

H

7

100

5

150

25

Total

590

870

Critical Path

Consider the following project network: Normal

  1. What is the total duration (days) of the project?
  2. What is the cost of crashing activity E by 1 day?
  3. How does crashing activity D by 2 days affect the overall duration of the project?
  4. If we want to reduce the overall duration of the project by 2 days, what is the least costly way to do it? How much will it affect the overall cost of the project?

0 4 A 4 4 D 13 9 15 15 H 22 7 15 22 0 4 6 Kev: 4 C 10 ES EF Start 6 10 F 15 5 10 15 End 4 10 LS LF 0 B 9 10 E 14 Bold Critical 9 4 14 G 17 3 19 22 1 10 15 19

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!