Question: Consider the following project network with normal activity times (in weeks) associated with each node. By adding more resources, some activities may be completed

Consider the following project network with normal activity times (in weeks) associated with each node. By adding more resources, some activities may be completed in less than their normal time. The crash times and associated costs per week are given in the table below. A B Reference: In-Class Paper Manufacturing Project The estimated project completion time is A. 2 weeks OB. 15 weeks OC. 13 weeks D. 14 weeks 3 F Activity A Crash Time (Weeks) Crash Cost/Week ($) 1 750 B 1 2,000 C 1 1,000 D 3 1,000 H E 2 1,000 F 2 500 G 2 1,500 HD 1 3,000
Step by Step Solution
There are 3 Steps involved in it
To determine the estimated project completion time we need to find the critical path of the project ... View full answer