Question: Consider the following project network, with task duration data provided: Which of the following is the slack in activity C ? A . 2 days

Consider the following project network, with task duration data provided:
Which of the following is the slack in activity C?
A.2 days
B.3 days
C.0 days
D.1 day
E.4 days