Question: QUESTION 1 8 Consider the following project network, with task duration data provided. Times listed are in weeks. The planned completion time is 2 2
QUESTION
Consider the following project network, with task duration data provided. Times listed are in weeks. The planned completion time is weeks; however, if task C is delayed for weeks and other tasks are still on schedule, how many weeks will this project be delayed beyond the planned completion time?
weeks.
week.
weeks.
weeks.
weeks.