Question: Consider the following project schedule: Activity Immediate Predecessor Time ES EF LS LF A - - 4 0 4 6 1 0 B - -
Consider the following project schedule:
Activity Immediate
Predecessor Time ES EF LS LF
A
B
C A
D B
E B
F C D
G C D
H E F
a Which activities are critical?
b Which activity has the most slack?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
