Question: Problem 1 The following represents a project with known activity times. All times are in weeks. Activity Immediate Predecessor Time A - 4 B -
Problem 1
The following represents a project with known activity times. All times are in weeks.
| Activity | Immediate Predecessor | Time |
| A | - | 4 |
| B | - | 3 |
| C | A, B | 2 |
| D | C | 7 |
| E | C | 4 |
Calculate the Critical Path and Project Completion Time.
First draw the network on a separate sheet of paper and then fill the following table:
| Activity | Immediate Predecessor | Time | ES | EF | LS | LF | Slack | Critical Path? |
| A | - | 4 |
|
|
|
|
|
|
| B | - | 3 |
|
|
|
|
|
|
| C | A, B | 2 |
|
|
|
|
|
|
| D | C | 7 |
|
|
|
|
|
|
| E | C | 4 |
|
|
|
|
|
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts