Question: Problem 1 The following represents a project with known activity times. All times are in weeks. Activity Immediate Predecessor Time A - 4 B -

Problem 1

The following represents a project with known activity times. All times are in weeks.

Activity

Immediate

Predecessor

Time

A

-

4

B

-

3

C

A, B

2

D

C

7

E

C

4

Calculate the Critical Path and Project Completion Time.

First draw the network on a separate sheet of paper and then fill the following table:

Activity

Immediate

Predecessor

Time

ES

EF

LS

LF

Slack

Critical

Path?

A

-

4

B

-

3

C

A, B

2

D

C

7

E

C

4

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!