Question: QUESTION 1 Consider the following project schedule: Activity Immediate Predecessor Time ES EF LS LF A -- 4 0 4 6 10 B -- 5
QUESTION 1
-
Consider the following project schedule:
Activity Immediate Predecessor Time ES EF LS LF A -- 4 0 4 6 10 B -- 5 0 5 0 5 C A 3 4 7 10 13 D B 8 5 13 5 13 E B 2 5 7 16 18 F C, D 3 13 16 15 18 G C, D 7 13 20 13 20 H E, F 2 16 18 18 20 Which activity has the most slack?