Question: QUESTION 1 Consider the following project schedule: Activity Immediate Predecessor Time ES EF LS LF A -- 4 0 4 6 10 B -- 5

QUESTION 1

  1. Consider the following project schedule:

    Activity Immediate Predecessor Time ES EF LS LF
    A -- 4 0 4 6 10
    B -- 5 0 5 0 5
    C A 3 4 7 10 13
    D B 8 5 13 5 13
    E B 2 5 7 16 18
    F C, D 3 13 16 15 18
    G C, D 7 13 20 13 20
    H E, F 2 16 18 18 20

    Which activity has the most slack?