Question: Consider the following project schedule. (i) You will construct the project network diagram (10 pts), (ii) Perfom CPM to determine the project completion time; you
Consider the following project schedule. (i) You will construct the project network diagram (10 pts), (ii) Perfom CPM to determine the project completion time; you need to show ES, EF, LS and LF, as well as the slack for each node. You will identify the critical path. (15pts.) This has to be done on a single sheet, scanned or photohraphed (vertically from above) and submitted as a PDF copy
The project completion time, T= days The critical paths is = (enter the path in the order of the letter tags without space, eg ADF etc) The slack at G = days The slack at B = days
| activity | predecessors | time (days) |
|---|---|---|
| A | -- | 11 |
| B | -- | 6 |
| C | A | 10 |
| D | A,B | 14 |
| E | C,D | 14 |
| F | D | 8 |
| G | E | 12 |
| H | E,F | 9
|