Question: Consider the following project schedule. (I) You will construct the project network diagram. (II) Perform CPM to determine the project completion time; you will need
Consider the following project schedule. (I) You will construct the project network diagram. (II) Perform CPM to determine the project completion time; you will need to show ES, EF, LS, and LF, as well as the slack for each node. You will identify the critical path. This has to be done on a sheet of paper.
A. The project completion time, T = ___________ days
B. The critical path is = ______________ (Enter the path in the order of the latter tags without space, eg ADF etc)
C. The slack at G = _________________ days
D. The slack at B = __________________ days
Project Schedule:
| Activity | Predecessors | Time (days |
| A | -- | 9 |
| B | -- | 6 |
| C | A | 10 |
| D | A,B | 13 |
| E | C,D | 14 |
| F | D | 8 |
| G | E | 14 |
| H | E,F | 9 |
Please show ALL work!!!
Thank you!!!
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts