Question: Consider the following project schedule. (I) You will construct the project network diagram. (II) Perform CPM to determine the project completion time; you will need

Consider the following project schedule. (I) You will construct the project network diagram. (II) Perform CPM to determine the project completion time; you will need to show ES, EF, LS, and LF, as well as the slack for each node. You will identify the critical path. This has to be done on a sheet of paper.

A. The project completion time, T = ___________ days

B. The critical path is = ______________ (Enter the path in the order of the latter tags without space, eg ADF etc)

C. The slack at G = _________________ days

D. The slack at B = __________________ days

Project Schedule:

Activity Predecessors Time (days
A -- 9
B -- 6
C A 10
D A,B 13
E C,D 14
F D 8
G E 14
H E,F 9

Please show ALL work!!!

Thank you!!!

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!