Question: Consider the following project. table [ [ Activity , Immediate,Activity Time ] , [ , Predecessor, ( days ) ] ] A 8 B

Consider the following project.
\table[[Activity,Immediate,Activity Time],[,Predecessor,(days)]]
A
8
B
6
C
A, B
4
D
B
5
E
C
7
F
C, D
7
G
D
9
E,F,G
6
Determine the critical path.
ACEH
BDFH
ACFH
 Consider the following project. \table[[Activity,Immediate,Activity Time],[,Predecessor,(days)]] A 8 B 6 C