Question: . Consider the following project. Task Description Immediate Predecessors Duration (Weeks) A Select office site - 3 B Create organizational and financial plan - 5
. Consider the following project.
| Task | Description | Immediate Predecessors | Duration (Weeks) |
| A | Select office site | - | 3 |
| B | Create organizational and financial plan | - | 5 |
| C | Determine personnel Requirements | B | 3 |
| D | Design Facility | A, C | 4 |
| E | Construct interior | D | 8 |
| F | Select personnel to move | C | 2 |
| G | Hire new employees | F | 4 |
| H | Move Records, Key Personnel, etc. | F | 2 |
| I | Make Financial arrangement | B | 5 |
| J | Train new personnel | H, E, G | 3 |
- Draw a project network
- What are the critical activities?
- Develop the activity schedule for the project
- What activity has the most slack time?