Question: . Consider the following project. Task Description Immediate Predecessors Duration (Weeks) A Select office site - 3 B Create organizational and financial plan - 5

. Consider the following project.

Task

Description

Immediate Predecessors

Duration (Weeks)

A

Select office site

-

3

B

Create organizational and financial plan

-

5

C

Determine personnel Requirements

B

3

D

Design Facility

A, C

4

E

Construct interior

D

8

F

Select personnel to move

C

2

G

Hire new employees

F

4

H

Move Records, Key Personnel, etc.

F

2

I

Make Financial arrangement

B

5

J

Train new personnel

H, E, G

3

  1. Draw a project network
  2. What are the critical activities?
  3. Develop the activity schedule for the project
  4. What activity has the most slack time?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!