Question: Given the Activity Table with their respective predecessors and duration (in weeks), prepare the following: Gantt Chart PERT Diagram Enumerated Paths List all paths (sequence

Given the Activity Table with their respective predecessors and duration (in weeks), prepare the following:

  • Gantt Chart
  • PERT Diagram
  • Enumerated Paths
    • List all paths (sequence of nodes) through the network and their lengths (total cost)
  • Critical Path
  • Shortest Time to Complete the Project

ACTIVITY

DESCRIPTION

PREDECESSORS

ACTIVITY TIME

A

Select Office Site

3

B

Create Organizational and Financial Plan

5

C

Determine Personnel Requirements

B

3

D

Design Facility

A,C

4

E

Construct Interior

D

8

F

Select Personnel to Move

C

2

G

Hire New Employees

F

4

H

Move Records, Key Personnel, etc.

F

2

I

Make Financial Arrangements with Institutions in Des Moines

B

5

J

Train New Personnel

H, E, G

3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!