Question: Given the Activity Table with their respective predecessors and duration (in weeks), prepare the following: Gantt Chart PERT Diagram Enumerated Paths List all paths (sequence
Given the Activity Table with their respective predecessors and duration (in weeks), prepare the following:
- Gantt Chart
- PERT Diagram
- Enumerated Paths
- List all paths (sequence of nodes) through the network and their lengths (total cost)
- Critical Path
- Shortest Time to Complete the Project
| ACTIVITY | DESCRIPTION | PREDECESSORS | ACTIVITY TIME |
| A | Select Office Site | 3 | |
| B | Create Organizational and Financial Plan | 5 | |
| C | Determine Personnel Requirements | B | 3 |
| D | Design Facility | A,C | 4 |
| E | Construct Interior | D | 8 |
| F | Select Personnel to Move | C | 2 |
| G | Hire New Employees | F | 4 |
| H | Move Records, Key Personnel, etc. | F | 2 |
| I | Make Financial Arrangements with Institutions in Des Moines | B | 5 |
| J | Train New Personnel | H, E, G | 3 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
