Question: Consider the following project tasks and their dependencies: Task | Predecessor | Dependency Type A|-|- B|-|- C|A|Finish-to-Finish DIA | Finish-to-Finish EB | Finish-to-Finish F|C, D
Consider the following project tasks and their dependencies: Task | Predecessor | Dependency Type A|-|- B|-|- C|A|Finish-to-Finish DIA | Finish-to-Finish EB | Finish-to-Finish F|C, D | Finish-to-Finish G|E, FI Finish-to-Finish Based on the given information, what does the "Finish-to-Finish" dependency type mean between tasks C and D? Select one: Task C can finish only after Task D finishes. O Task C must finish before Task D can start. O Task C must finish at the same time as Task D. O Task C can finish anytime before Task D finishes.