Question: Consider the following project tasks and their respective durations: Task | Predecessor | Duration (weeks) A|-12 B|-|4 C|A|3 D|A|5 E|B|4 F|C, D | 2 G|E,

Consider the following project tasks and their respective durations: Task | Predecessor | Duration (weeks) A|-12 B|-|4 C|A|3 D|A|5 E|B|4 F|C, D | 2 G|E, F 3 H|G|2 Based on the given information, what is the longest sequence of critical tasks in the project using the Critical Path Method (CPM)?