Question: In order to crash the project given below by 4 days, what will be the minimum cost of crashing? ACTIVITY NORMAL TIME (DAYS) CRASH TIME

In order to crash the project given below by 4

days,

what will be the minimum cost of

crashing?

ACTIVITY

NORMAL TIME (DAYS)

CRASH TIME (DAYS)

NORMAL COST ()

CRASH COST []

IMMEDIATE PREDECESSOR(S)

A

6

5

200

325

-

B

5

4

1000

1200

-

C

4

2

600

750

-

D

4

2

1000

1350

A, B

E

7

4

1100

1775

C

The minimum cost of crashing is

nothing

(enter your response as a WHOLE

NUMBER).