Question: In order to crash the project given below by 4 days, what will be the minimum cost of crashing? ACTIVITY NORMAL TIME (DAYS) CRASH TIME
In order to crash the project given below by 4
days,
what will be the minimum cost of
crashing?
| ACTIVITY | NORMAL TIME (DAYS) | CRASH TIME (DAYS) | NORMAL COST () | CRASH COST [] | IMMEDIATE PREDECESSOR(S) | ||
| A | 6 | 5 | 200 | 325 | - | ||
| B | 5 | 4 | 1000 | 1200 | - | ||
| C | 4 | 2 | 600 | 750 | - | ||
| D | 4 | 2 | 1000 | 1350 | A, B | ||
| E | 7 | 4 | 1100 | 1775 | C | ||
The minimum cost of crashing is
nothing
(enter your response as a WHOLE
NUMBER).