Question: Consider the following projects: Project C1 C2 C3 C4 JA -1000 +600 +200 +200 +1000 B -1000 +200 +200 +600 +1000 -1300 +100 +100 +100

Consider the following projects: Project C1 C2 C3 C4 JA -1000 +600 +200 +200 +1000 B -1000 +200 +200 +600 +1000 -1300 +100 +100 +100 +1600 D -1300 O +300 |+300 +1600 a) Calculate the payback period for each project. Explain the pitfalls of this method.(5) b) If the standard payback period is 2 years, which project will you select? Will our answer be different if the standard payback period is 3 years. (5) c) If the cost of capital is 10%, compute the discounted payback for each project? Which projects will you recommend if the standard payback period is 2 years, 3 years (5) 3 d) Compute the NPV of each project? Which projects will you recommend
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
