Question: Consider the following scenario: The table below represents a project being analyzed by the critical path method. Activity Immediate Predecessor Duration (In weeks) B C

Consider the following scenario: The table below
Consider the following scenario: The table below
Consider the following scenario: The table below represents a project being analyzed by the critical path method. Activity Immediate Predecessor Duration (In weeks) B C D E F A A B B 5 9 4 7 5 5 3 3 7 4 OE- CD GE EF HIJ K The "Late Start" of activity "E" is * 3 10 6 O 11