Question: Consider the following scenario: The table below represents a project being analyzed by the critical path method. Activity Immediate Predecessor Duration (in weeks) B D

Consider the following scenario: The table below
Consider the following scenario: The table below
Consider the following scenario: The table below represents a project being analyzed by the critical path method. Activity Immediate Predecessor Duration (in weeks) B D E F G H 1 J K A A B B D C D GE EF HIJ 5 9 4 7 S 5 5 3 7 4 The "Early Start" of activity "I" is * O 17 16 14 15