Question: Consider the following scenario: The table below represents a project being analyzed by the critical path method. Activity Immediate Predecessor Duration (In weeks) A B

Consider the following scenario: The table below
Consider the following scenario: The table below
Consider the following scenario: The table below represents a project being analyzed by the critical path method. Activity Immediate Predecessor Duration (In weeks) A B D E F G II 1 A A B B 5 9 4 7 5 5 S 3 7 4 -- CD GE EF HIJ K The "Early Finish" of activity "J" is * 17 O 21 11 19