Question: The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network. Complete the table below. Identify
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network.
Complete the table below.
Identify the critical path(s).
What is the duration of the critical path?
Calculate the amount of slack time at activity D and F.
If activity D was delayed by ten time units, what would be the impact on the project duration?
If activity F was delayed by ten time units, what would be the impact on the project duration?