Question: Consider the following sequential production process with four machines A, B, C, and D. Machine A Machine B Machine C Machine D Framer Handler Stringer

Consider the following sequential production process with four machines A, B, C, and D.

Machine A Machine B Machine C Machine D Framer Handler Stringer Finisher 5 minutes 3 minutes 10 minutes 2 minutes

All flow units need to move through all the above stages sequentially, with the designated task time indicated above. Assume there are only two workers to operate these machines, meaning at least one worker needs to operate multiple machines. What is the optimal process capacity for this process?

Group of answer choices

5 units per hour

4 units per hour

2 units per hour

6 units per hour

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!