Question: Consider the following sequential production process with four machines A, B, C, and D (4 workers operate these machines respectively, one worker per machine). Machine
Consider the following sequential production process with four machines A, B, C, and D (4 workers operate these machines respectively, one worker per machine).
Machine AMachine BMachine CMachine D
FramerHandlerStringerFinisher
5 minutes3 minutes10 minutes2 minutes
All flow units need to move through all the above stages sequentially, with the designated task time indicated above. How long would it take to produce 101 units, starting with an empty system?
Group of answer choices
1020
1010
1030
1040