Question: Consider the following sequential steps in a process. The facility operates 8 hours per day. What is the maximum output per 8 hours? Step 1

Consider the following sequential steps in a process. The facility operates 8 hours per day. What is the maximum output per 8 hours? Step 1: 9 min Step 2: 12 min Step 3: 15 min Step 4: 3 min.
40 units
160 units
32 units
53 units
69 units