Question: Question 5 1 Point Consider the following sequential steps in a process. The facility operates 7 . 5 hours per day. What is the maximum

Question 51 Point
Consider the following sequential steps in a process. The facility operates 7.5 hours per day. What is the maximum output per 7.5 hours shift? Step 1: 7 min Step 2: 5 min Step 3: 6 min Step 4: 3 min.