Question: Consider the following sequential steps in a process. The facility operates 8 hours per day. What is the maximum output per 8 hours? Step 1:
Consider the following sequential steps in a process. The facility operates 8 hours per day. What is the maximum output per 8 hours? Step 1: 2 min Step 2: 3 min Step 3: 4 min Step 4: 5 min. 120 units 96 units 53 units 240 units 160 units