Question: Consider the following table. Activity Duration Depends on Resource Type A 3 days SA B 1 day A SD C 2 days A SD D
Consider the following table.
| Activity | Duration | Depends on | Resource Type |
| A | 3 days |
| SA |
| B | 1 day | A | SD |
| C | 2 days | A | SD |
| D | 4 days | A | SD |
| E | 3 days | B | SC |
| F | 3 days | C | SC |
| G | 6 days | D | SC |
| H | 3 days | E,F,G | SA |
| SA System Analyst; SD System Designer; SC System Coder | |||
- (10 pts) Draw up a PERT and identify critical path.
- (10 pts) Draw up a resource table showing the number of each type of resource needed on each day of the project.
- (10 pts) Draw up histograms for both SD and SA. Assume that there are no resource restrictions.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts