Question: Consider the following table. Activity Duration Depends on A 3 days B 1 day A 2 days A D 4 days A E 3 days

Consider the following table. Activity Duration

Consider the following table. Activity Duration Depends on A 3 days B 1 day A 2 days A D 4 days A E 3 days B F 3 days G 6 days D H 3 days E,F,G SA = system analyst; SD = system designer; SC = system coder Resource Type SA SD SD SD SC SC SC SA a. b. Draw up a PERT chart for the activities above, and identify the critical path (PERT). Draw up a resource table showing the number of each type of resource needed on each day of the project Generate resource histogram for both SD and SC. C