Question: Draw the Network Diagram (critical path) using the following table: Activity Predecessor Duration A 28 B 44 C 26 D 30 E A 51 F

Draw the Network Diagram (critical path) using the following table:

Activity Predecessor Duration
A 28
B 44
C 26
D 30
E A 51
F A 69
G A 87
I E 79
J E 58
K E 29
L B 85
M B 59
N B 54
O B 70
P L 85
Q L 84
S C, G, I, M 85
T C, G, I, M 38
U C, G, I, M 27
V D, J, N, P, S 82
W D, J, N, P, S 77
X F, K, O, Q, T, V 80

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!