Question: Consider the following tasks shown in table below. Draw an Activity-on-Arrow (AOA) network diagram representing the project. Put the node numbers in circles and draw
Consider the following tasks shown in table below. Draw an Activity-on-Arrow (AOA) network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time
| Activity | Initial Node | Final Node | Estimated Duration |
| A | 1 | 2 | 2 |
| B | 2 | 3 | 2 |
| C | 2 | 4 | 3 |
| D | 2 | 5 | 4 |
| E | 3 | 6 | 2 |
| F | 4 | 6 | 3 |
| G | 5 | 7 | 6 |
| H | 6 | 8 | 2 |
| I | 6 | 7 | 5 |
| J | 7 | 8 | 1 |
| K | 8 | 9 | 2 |
*All duration estimated times are in days; and the network proceeds from Node 1 to Node 9.
Question Two ( 0.5 Mark )
Write all possible paths in the diagram of question one. What is the critical path for this project and how long is it?