Question: Consider the following tasks shown in table below. Draw an Activity-on-Arrow (AOA) network diagram representing the project. Put the node numbers in circles and draw

Consider the following tasks shown in table below. Draw an Activity-on-Arrow (AOA) network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time

Activity

Initial Node

Final Node

Estimated Duration

A

1

2

2

B

2

3

2

C

2

4

3

D

2

5

4

E

3

6

2

F

4

6

3

G

5

7

6

H

6

8

2

I

6

7

5

J

7

8

1

K

8

9

2

*All duration estimated times are in days; and the network proceeds from Node 1 to Node 9.

Question Two ( 0.5 Mark )

Write all possible paths in the diagram of question one. What is the critical path for this project and how long is it?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!