Question: Consider the following tasks. Tasks A, B, C, D, E, F, and G have durations of 5, 4, 6, 2, 7, 1, and 5 weeks,
Consider the following tasks. Tasks A, B, C, D, E, F, and G have durations of 5, 4, 6, 2, 7, 1, and 5 weeks, respectively. Task A has no predecessor. Task B has A as its predecessor. Both C and D have B as their predecessor. Task E's predecessor is C. Task F's predecessors are C and D, while Task G's predecessors are E and F. Given this information, what is the slack for Task D?
Group of answer choices
a. 0 weeks
b. 3 weeks
c. 6 weeks
d. 10 weeks