Question: Consider the following tasks. Tasks A, B, C, D, E, F, and G have durations of 5, 4, 6, 2, 7, 1, and 5 weeks,

Consider the following tasks. Tasks A, B, C, D, E, F, and G have durations of 5, 4, 6, 2, 7, 1, and 5 weeks, respectively. Task A has no predecessor. Task B has A as its predecessor. Both C and D have B as their predecessor. Task E's predecessor is C. Task F's predecessors are C and D, while Task G's predecessors are E and F. Given this information, what is the slack for Task D?

Group of answer choices

a. 0 weeks

b. 3 weeks

c. 6 weeks

d. 10 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!