Question: Consider the following tasks. Tasks A, B, C, D, E, F, and G have durations of 5, 4, 6, 2, 7, 1, and 5 weeks,

Consider the following tasks. Tasks A, B, C, D, E, F, and G have durations of 5, 4, 6, 2, 7, 1, and 5 weeks, respectively. Task A has no predecessor. Task B has A as its predecessor. Both C and D have B as their predecessor. Task E's predecessor is C. Task F's predecessors are C and D, while Task G's predecessors are E and F. Given this information, what is the duration of the critical path?

Group of answer choices

a. 27 weeks

b. 21 weeks

c. 25 weeks

d. 17 weeks