Question: Consider the following tasks. Tasks A, B, C, D, E, F, and G have durations of 5,4,2,2,3,4, and 5 weeks, respectively. Task A has no

Consider the following tasks. Tasks A, B, C, D,
Consider the following tasks. Tasks A, B, C, D, E, F, and G have durations of 5,4,2,2,3,4, and 5 weeks, respectively. Task A has no predecessor. Task B has A as its predecessor. Both C and D have B as their predecessor. Task E's predecessor is C. Task F's predecessors are C and D, while Task G's predecessors are E and F. Given this information, what is the critical path? b. Start-A-B-D-F-G-End a. Start-A-B-D-E-G-End c. Start-A-B-E-F-G-End d. Start-A-B-C-E-G-End