Question: Consider the following two projects. The crossover rate between the two projects is %. CFs for Project A CFs for Project B yr. O -
Consider the following two projects. The crossover rate between the two projects is %. CFs for Project A CFs for Project B yr. O - 1200 - 1000 yr. 1 1,327 1,118 Margin of error for correct responses: +/-.01 (%) Rounding and Formatting instructions: Do not enter dollar signs, % signs, or commas in your response. Do not round any intermediate work, but round your final response to 2 decimal places (example: if your answer is 12.34567%, you should enter 12.35)