Question: Consider the following work breakdown structure: 33 2 points Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A,B,C D 38 50 62 B

Consider the following work breakdown structure:

Consider the following work breakdown structure: 33 2 points Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A,B,C D 38 50 62 B E 90 99 108 c End 85 100 115 D F 19 25 31 E End 91 100 115 F End 62 65 68 02:06:55 What is the estimated standard deviation in the time for activity E? Multiple Choice 24 days o o 2 days 16 days