Question: Consider the following work breakdown structure of Chiang's project: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A,B - - - A C,D
Consider the following work breakdown structure of Chiang's project:
| Time Estimates (days) |
| Activity | Precedes | Optimistic | Most Likely | Pessimistic | ||||||
| Start | A,B | - | - | - | ||||||
| A | C,D | 41 | 47 | 71 | ||||||
| B | C | 90 | 99 | 108 | ||||||
| C | E,F | 92 | 98 | 116 | ||||||
| D | F | 7 | 28 | 31 | ||||||
| E | End | 91 | 100 | 115 | ||||||
| F | End | 62 | 65 | 68 | ||||||
1) Use the given information, what is the expected (mean) time to complete the activity C?
2) Use the given information, what is the variance of the activity C?
3) Use the given information, what is the expected duration for path A-D-F?
4) Used the expected time of an activity to create an activity on node (AON) network diagram, what is the slack of the activity A?
5) Use the given information, what is the expected (mean) time for project completion?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock