Question: Consider the following work breakdown structure of Chiang's project: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A,B - - - A C,D

Consider the following work breakdown structure of Chiang's project:

Time Estimates (days)
Activity Precedes Optimistic Most Likely Pessimistic
Start A,B - - -
A C,D 41 47 71
B C 90 99 108
C E,F 92 98 116
D F 7 28 31
E End 91 100 115
F End 62 65 68

1) Use the given information, what is the expected (mean) time to complete the activity C?

2) Use the given information, what is the variance of the activity C?

3) Use the given information, what is the expected duration for path A-D-F?

4) Used the expected time of an activity to create an activity on node (AON) network diagram, what is the slack of the activity A?

5) Use the given information, what is the expected (mean) time for project completion?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!