Question: Consider the following work breakdown structure: Activity Start B C D Time Estimates (days) Precedes Optimistic Most Likely Pessimistic A,B,C D 38 50 62 E

Consider the following work breakdown structure:
Consider the following work breakdown structure:
Consider the following work breakdown structure: Activity Start B C D Time Estimates (days) Precedes Optimistic Most Likely Pessimistic A,B,C D 38 50 62 E 90 99 108 End 85 100 115 F 19 25 31 End 91 100 115 End 62 65 68 E F What is the estimated expected (mean) time for project completion? Multiple Choice O 440 days O 200 days 199 days 140 days 100 days