Question: Consider the following work breakdown structure: Activity Start Duration Estimates (Days) Optimistic Most Likely Pessimistic U Precedes UV W W, X Z V W 35

 Consider the following work breakdown structure: Activity Start Duration Estimates (Days)

Consider the following work breakdown structure: Activity Start Duration Estimates (Days) Optimistic Most Likely Pessimistic U Precedes UV W W, X Z V W 35 28 26 28 26 36 50 40 35 40 29 60 65 52 44 52 38 84 Y N NK End What is the estimated standard deviation in the time for activity Z

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!