Question: Consider the following work breakdown structure: Given a due date of 210 days, what is the probability of completing the project after 225 days? Time
Consider the following work breakdown structure: Given a due date of 210 days, what is the probability of completing the project after 225 days?
|
| Time Estimates (days) | |||||||||
| Activity | Precedes | Optimistic | Most Likely | Pessimistic | ||||||
| Start | A,B |
| - |
|
| - |
|
| - |
|
| A | C,D |
| 44 |
|
| 50 |
|
| 56 |
|
| B | D |
| 45 |
|
| 60 |
|
| 75 |
|
| C | E |
| 42 |
|
| 45 |
|
| 48 |
|
| D | F |
| 31 |
|
| 40 |
|
| 49 |
|
| E | F |
| 27 |
|
| 36 |
|
| 39 |
|
| F | End |
| 58 |
|
| 70 |
|
| 82 |
|
| 0.3 | ||
| 0.5 | ||
| 0.9 | ||
| 1 | ||
| 0 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
