Question: Consider the following work breakdown structure: Given a due date of 210 days, what is the probability of completing the project after 225 days? Time

Consider the following work breakdown structure: Given a due date of 210 days, what is the probability of completing the project after 225 days?

Time Estimates (days)

Activity

Precedes

Optimistic

Most Likely

Pessimistic

Start

A,B

-

-

-

A

C,D

44

50

56

B

D

45

60

75

C

E

42

45

48

D

F

31

40

49

E

F

27

36

39

F

End

58

70

82

0.3

0.5

0.9

1

0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!