Question: Consider the following work breakdown structure: Given a due date of 210 days, what is the latest you can start activity E without delaying the

Consider the following work breakdown structure: Given a due date of 210 days, what is the latest you can start activity E without delaying the project?

Time Estimates (days)

Activity

Precedes

Optimistic

Most Likely

Pessimistic

Start

A,B

-

-

-

A

C,D

44

50

56

B

D

45

60

75

C

E

42

45

48

D

F

31

40

49

E

F

27

36

39

F

End

58

70

82

130

105

95

100

140